... Skip to main content

Andries Olivier Durbanville Quadriplegic Centre

Registered NPO 039-707 · PBO 930029333 021 975 5459 quads@telkomsa.net
18 Hafele Street, Durbanville
🚨 Urgent Structural Appeal

Staff Quarters Repair Appeal for HAODQC

A registered structural engineer has confirmed serious floor settlement and wall cracking in our staff quarters. We urgently need the community's help — cash, building materials, skilled labour, and professional expertise.

Engineer: J.S. van Eeden (Pr. Eng.) · JVE Consulting · 7 April 2026

50mm Floor Settlement Confirmed by structural engineer
233m² Total Paint Area 158.7m² internal · 75.2m² external
4 Ways to Help Cash · Materials · Labour · Skills
NPO Registered & Verified 039-707 · PBO 930029333
The Problem

Serious Structural Damage to Staff Housing

Our staff quarters — housing the care staff who look after our 12 residents 24 hours a day — have sustained significant structural damage. A registered professional engineer was called in to assess the building and has confirmed the severity of the problem.

Without functioning staff accommodation, we cannot maintain 24-hour care for our residents. This is an urgent matter that directly threatens the wellbeing of everyone at HAODQC.

⚠ Approximately 50mm floor settlement in key areas

⚠ Significant wall cracking throughout the structure

⚠ Perimeter drainage issues contributing to movement

📋 Scope of Work Required

  • Floor slab repair and levelling of settled areas
  • Wall stabilisation and crack filling
  • Internal painting — 158.7m²
  • External painting — 75.2m²
  • Perimeter hard standing installation
  • Drainage improvements around the building
Engineer's Report

Professional Assessment

The building was formally assessed by a registered professional engineer in April 2026.

🔧 Engineer Details

Name: J.S. van Eeden (Pr. Eng.)

Firm: JVE Consulting

Date: 7 April 2026

Status: Contractor quotes pending

📄 Primary Findings

  • Floor slab settlement of approximately 50mm
  • Resultant wall cracking throughout structure
  • Inadequate perimeter drainage
  • Immediate remedial work recommended

The floor slab has experienced significant settlement of approximately 50mm in key areas, resulting in visible cracking to the walls and potential long-term structural instability if remedial work is not undertaken promptly. Immediate attention is recommended.

— J.S. van Eeden (Pr. Eng.), JVE Consulting — April 2026
Damage Photos

The Extent of the Damage

Click any image to view it larger. These photos were taken during the structural assessment in April 2026.

How to Help

Four Ways to Contribute

Every form of support is welcome and gratefully received.

💰

Cash Donation

Donate by EFT to fund materials, labour and contractor costs. Every rand counts. Section 18A receipts available.

🧱

Building Materials

Concrete, screed, plaster, paint, and perimeter materials. Contact us if you can supply or source materials at cost.

🔨

Skilled Labour

Concrete work, plastering, painting. Volunteer your team or donate a day's work on this critical project.

📐

Professional Services

Quantity surveying, project management, engineering, or legal services donated pro bono are invaluable.

```
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.